/ Field notes · v1.0

Power lines. Signals. When the lift is critical.

Working notes we use before a study starts. Written in JMR language. This page is not ASME B30.5, not BS 7121, and not your site procedure. Buy and apply the current standard that governs that crane on that ground.

Do not lift from this page. Clearance numbers below are the public OSHA operating minima (29 CFR 1926.1408). Utility voltage, boom envelope and local rules can demand more. If the boom can reach the line, stop and plan it as a critical lift.
01 — Energized lines

Keep the crane out of the zone.

Preferred condition: the line is isolated, grounded and confirmed by the utility on site. If the line stays live, treat clearance as a hard hold-point — not a guess from the cab.

Minimum clearance while the crane is operating, from OSHA 29 CFR 1926.1408 Table A. Metres in brackets are conversions of the published feet values.

Nominal voltage (kV, AC)Clearance while operating
Up to 5010 ft (3.1 m)
Over 50 to 20015 ft (4.6 m)
Over 200 to 35020 ft (6.1 m)
Over 350 to 50025 ft (7.6 m)
Over 500 to 75035 ft (10.7 m)
Over 750 to 1,00045 ft (13.7 m)
Over 1,000Set with the utility or a qualified electrical engineer

Travel / transit with no load and boom lowered is a different table (OSHA 1926.1408 Table T). Distances shrink, but only in that configuration. Do not use travel figures while hoisting.

Nominal voltage (kV, AC)Clearance in travel, boom down, no load
Up to 0.754 ft (1.2 m)
Over 0.75 to 506 ft (1.8 m)
Over 50 to 34510 ft (3.1 m)
Over 345 to 75016 ft (4.9 m)
Over 750 to 1,00020 ft (6.1 m)
Over 1,000Set with the utility

Source: OSHA 29 CFR 1926.1408, public US regulation. ASME B30.5 has its own clauses on the same subject — we do not reproduce them here. Always take the stricter of the applicable documents.

02 — Signals

One language. Agreed before the hook moves.

Radio can be primary. Hand signals stay as backup. The banksman and the operator brief the same set. If comms drop, the lift stops — there is no “guess the last order”.

These are common industry signals described in JMR words. They are not official ASME plates. Train the crew on the set that the site procedure names.

03 — Critical lifts

When we will not treat it as routine.

“Critical” is a company and client word as much as a code word. ASME B30.5 Appendix A is non-mandatory. If the client, the duty holder or BS 7121 is stricter, that rule wins. On JMR studies we treat a lift as critical — written plan, named AP, pre-lift meeting — when any of these is true:

A critical plan, in our work, always names the total lifted weight (load + block + below-hook gear), the crane duty and radius, the rigging geometry, the path and the ground or vessel support. It is signed. The crew meets on that revision before the first hoist. If the plan changes on the day, the meeting runs again — we do not “carry on and write it later”.

04 — Questions

Field notes are not the code.

Is this ASME B30.5?

No. We do not republish ASME text, tables or figures. Buy B30.5 from ASME if that volume applies to the crane. This page is a JMR briefing aid.

Why OSHA numbers then?

Those operating and travel distances are published in US federal regulation and are public. They are a useful floor. They are not automatically legal on an Angolan platform, a UK site under LOLER, or a Gulf project under company lifting procedure.

Will JMR sign a lift because I ticked this page?

No. A signed plan is a paid study for that load, that crane and that site.

05 — Next

Near a line, or over 75%. Send the brief.

Voltage, radius, chart and a sketch of the path is enough for a free preliminary view. If it is critical, we will say so before we quote.

contact@jmrlifting.com · Field notes v1.0 · August 2026